G1000 System Maintenance Manual – Diamond DA40/40F Page 5-23
190-00545-01 Revision G
Step 8: Verify servo type
This step checks to ensure the servos are correct type.
Verify servos are correct type.
Step 9: Verify servo first certification data
This step checks to ensure the servos and the GIAs have the same certification gains.
Reload the certification gains to all GIAs and servos.
Step 10: Verify servo second certification data
This step checks to ensure the servos and the GIAs have the same certification gains.
Reload the certification gains to all GIAs and servos.
Step 11: Updating servo RTC
This step sets the servo system time to the GIA system time.
Step 12: Verify servo PFT status
This step checks to ensure all servos have passed their own pre-flight test.
Step 13: Verify AP disconnect enabled
This step checks to ensure GIA 1, GIA 2, and all servos are connected to the 28 volt autopilot
disconnect.
Ensure the autopilot disconnect is connected to all GIAs and servos and is registering 28 volts.
Ensure the autopilot disconnect switch is not pressed.
Step 14: Verify servo validity
This step checks to ensure all servos are online and communicating with valid data.
Ensure all servos are turned on and communicating.
Step 15: Verify cross GIA PFT is completed
This step checks to ensure the cross-side GIA is also on step 14.
Cycle power on all servos and GIAs.
Ensure the PFD and MFD are turned on.
Step 16: PFT completed
The pre-flight test is successfully completed.
Step 17: PFT failed
The pre-flight test has failed.